Project Networking provides the necessary tools to monitor project progress. Considerable time and effort is expended developing successful project networks. Refer to exercise 9 in chapter 6 of the te

You are creating a customer database for the Modesto Nuts minor league baseball team. Draw a project network given the information below. Complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? How sensitive is the network schedule? Calculate the free slack and total slack for all noncritical activities.

ID Description Predecessor (days)

A Systems design None 2

B Subsystem A Design A 1

C Subsystem B Design A 1

D Subsystem C Design A 1

E Program A B 2

F Program B C 2

G Program C D 2

H Subsystem A Test E 1

I Subsystem B Test F 1

J Subsystem C Test G 1

K Integration H, I, J 2

L Integration test K 1