Activity ID | Activity | Immediate Predecessor | Duration in days | Resource | Work Hours per Day |
Evaluate freezers |
| Alcides | |||
Chart temperatures |
| Joan | |||
Review service record |
| Alcides |
| ||
Consult with HVAC engineer | A, B, C | Alcides |
| ||
Develop construction plan | 10 | Joan |
| ||
Complete IC assignment | Alcides |
| |||
Complete ROI analysis | Joan |
| |||
Conduct regulatory review | Joan |
| |||
Obtain construction approval | F, G, H | Alcides |
WBS | Activity | Immediate Predecessor | Estimated Duration in weeks | Resource |
1 | Process Improvement Project |
|
|
|
1.1 | Operational definition |
|
|
|
1.1.1 | Research literature |
| Becky | |
1.1.2 | Identify and define terms | 1.1.1 | Ann | |
1.1.3 | Obtain approval of definition | 1.1.2 | Clive | |
1.2 | Target Selection |
|
|
|
1.2.1 | Solicit partners for pilot |
| Ann | |
1.2.2 | Hold brainstorming meeting | 1.2.1 | Becky | |
1.2.3 | Identify characteristics of targets | 1.2.2, 1.3.1 | Ann | |
1.2.4 | Obtain approval of partners | 1.2.3, 1.1.2, 1.3.4 | Clive | |
1.3 | Question set |
|
|
|
1.3.1 | Identify process group members |
| Clive | |
1.3.2 | Develop question set | 1.2.3 | Ann | |
1.3.3 | Prototype and validate question set | 1.3.2 | Becky | |
1.3.4 | Add partners | 1.3.1, 1.2.1 | Becky | |
1.4 | Pilot process |
|
|
|
1.4.1 | Schedule with target audience | 1.2.4 | Becky | |
1.4.2 | Conduct beta test | 1.3.4, 1.2.4 | Clive | |
1.4.3 | Process feedback from target audience | 1.4.2 | Ann | |
1.4.4 | Conduct pilot | 1.4.3 | Clive | |
1.4.5 | Analyze results | 1.4.4 | Clive |