Unit VI Project I will pay 100.00 for this 4 part question dealing with Project Management. I have included the template for the exercise as well as 7 pages of required reading.This assignment c

Running head: UNIT VI PROJECT 0










Unit VI Project

Your Name

Columbia Southern University


Part 1


Develop an in-depth schedule for the project you selected and used to develop the statement of work and work breakdown structure in Unit III. Please refer to the Integrated Project in Chapter 10 on page 363 (Project Scheduling) of the textbook for more information. Be sure to include the following components:


  • an activity precedence diagram,

  • an activity duration table, and

  • a network diagram and Gantt charts.



Part 2


Please complete Case Study 10.1: Project Scheduling at Blanque Check Construction on page 360 of the textbook, and answer the three questions at the end.



Part 3


Develop a network activity chart, and identify the critical path for a project based on the information provided in the Gantt chart below. Draw the activity network as a Gantt chart. What is the expected duration of the project?


Activity

Expected Duration

Predecessor

A

5 days

----

B

10 days

A

C

8 days

A

D

1 day

A

E

5 days

B, C

F

10 days

D, E

G

14 days

F

H

3 days

G

I

12 days

F

j

6 days

H, I



Part 4


Using the information provided in the Gantt chart below, construct the project activity network using the activity-on-node (AON) methodology, and label each node. Identify the critical path and other paths through the network.


Activity



Duration


Predecessors

A



3


--

B



5


A

C



7


A

D



3


B, C

E



5


B

F



4


D

G



2


C

H



5


E, F, G

Activity

Duration

ES

EF

LS


LF

Slack

A

3

0

3

0


0

--

B

5

3

8

8


13

5

C

7

3

10

3


10

--

D

3

10

13

13


13

--

E

5

8

12

13


17

5

F

4

13

17

13


17

G

2

10

12

15


17

5

H

5

17

22

17


22

--



References