1) Jack, the owner and manager of a Health Care Company that manufactures medical supplies, wants to monitor usage at Workcenter 3, which is a...

  1. Jack, the owner and manager of a Health Care Company that manufactures medical supplies, wants to monitor usage at Workcenter 3, which is a bottleneck in the system. He has collected data on the planned and actual input and output.


Input Information (in hours)


4

5

6

7

8

Planned Input

40

50

50

60

60

Actual Input

45

45

45

55

60

Deviation

Cumulative Deviation


Output Information (in hours)


4

5

6

7

8

Planned output

70

70

70

70

70

Actual output

60

60

60

60

60

Deviation

Cumulative Deviation

Blocklog 75 hours


Calculate the percentage of planned output needed to complete the planned inputs at Workcenter 3.