I will pay 50.00 for the following essay, required reading attached. Unit VII Essay Use the projects you completed in Units III and VI to conduct a preliminary risk analysis. Use a qualitative and a q

Running head: UNIT VI PROJECT 0










Unit VI Project

Your Name

Columbia Southern University


Part 1

The Project Schedule

Activity Precedence Diagram (T.I. Liu, 1996)

Earliest Start Time

Duration

Earliest Finish Time

 

1 week

2 months

7 weeks

<Task Description>

Development of a Software for Online Store

Latest Start Time

Float

Latest Finish Time

10 days

0 weeks

9 weeks


Activity Duration Table

Duration

Activity

Optimistic

Likely

Pessimistic

Est. Duration

A

2

2

4

2

B

3

6

6

1

C

5

5

7

2

D

4

4

7

2

E

2

6

8

1


Network Diagram

I will pay 50.00 for the following essay, required reading attached. Unit VII Essay Use the projects you completed in Units III and VI to conduct a preliminary risk analysis. Use a qualitative and a q 1


Gantt chart



Part 2

Please complete Case Study 10.1: Project Scheduling at Blanque Check Construction on page 360 of the textbook, and answer the three questions at the end.

Project Network (Blackburn, 2002).

Steps

Activity

Activity Description

Step 1

Vendor selection

The vendor are selected in this very first phase

Step 2

Contract signing

Contracts with the selected vendors are made

Step 3

Requirement gathering

Requirements gathering is done in this activity

Step 4

Requirement analysis

Gathered requirements are analyzed

Step 5

Planning scope

Scope of the project is planned

Step 6

Planning budget

Budget available for the project is defined here

Step 7

Planning time

Time required to complete the project is planned

Step 8

Design

Design of the product is worked upon

Step 9

Implementation

Design is implemented

Step 10

Development

Development of the product starts

Step 11

Prototype testing

Prototype of the product is made for testing

Step 12

Engineering

Engineering related to the product is carried here as in this case it is civil engineering for the construction of properties

Step 13

Subcontract signing

Subcontracts to different local contractors are made in order to divide the work load

Step 14

Quality testing

The quality of the product is tested in this activity

Step 15

Environmental Testing

The buildings made are tested in accordance with the suitability to natural environment

Step 16

Addressing shortcomings

Discovered shortcomings are removed

Step 17

Final Testing

Final testing of the product is carried in this activity prior to the release

Step 18

Release

The tested product is delivered to the client

Step 19

Maintenance

The maintenance work of the product is performed in accordance with the time constraints defined in the contract

Step 20

Project termination

The project is closed officially



Question No. 2

Expert Opinion for Calculation of Duration Estimation for the Project Activities

This approach can be used by contacting different estate experts that have the idea of that particular market in which the construction will take place. The opinion of such people can matter a lot in the project and such experts should also be made to give opinions that are well aware to the construction projects in that site.

Past History for Calculation of Duration Estimation for the Project Activities

The past history can also provide sufficient data regarding the duration estimates for the project activities as it can efficiently predict the duration of future activities on the basis of the pattern found in past projects (Saunders, 1990).

Mathematical Calculation for Calculation of Duration Estimation for the Project Activities

The mathematical calculations are also an effective tool for the duration estimates. The time limits can be utilized in the mathematical equations to predict the duration of various activities accurately.

Question No. 3

Joe should consider following issues before choosing between the methods of AON and AOA:

  • The feasibility of construction projects in that particular area

  • Analysis of available resources like time and money

  • Analysis of past projects

  • Estimating available workforce

  • Demands and needs of the client



Part 3

Network Activity Chart (Andronov, 2013)

I will pay 50.00 for the following essay, required reading attached. Unit VII Essay Use the projects you completed in Units III and VI to conduct a preliminary risk analysis. Use a qualitative and a q 2

The expected duration of the project is 7 weeks.

Part 4

Project Activity Network

I will pay 50.00 for the following essay, required reading attached. Unit VII Essay Use the projects you completed in Units III and VI to conduct a preliminary risk analysis. Use a qualitative and a q 3

Critical Path and other Paths through the Network (ARSHAM, 1999)

The critical path through the network is C–G–H that has the longest resulting value of 14.

The other paths like B-D-F and D-F-H can be identified as subcritical with the values of 12 for both.

References

Andronov, A., & Rebezova, M. (2013). Polynomial approximation of the activity completion time distribution in network chart. Automatic Control And Computer Sciences47(4), 192-201. doi: 10.3103/s0146411613040020

Arsham, H. (1999). Stability analysis of the critical path in project activity networks. Civil Engineering And Environmental Systems15(4), 305-334. doi: 10.1080/02630259908970245

Blackburn, S. (2002). The project manager and the project-network. International Journal Of Project Management20(3), 199-204. doi: 10.1016/s0263-7863(01)00069-2

G Saunders, R. (1990). Project management in R&D: the art of estimating development project activities. International Journal Of Project Management8(1), 45-50. doi: 10.1016/0263-7863(90)90008-y

Liu, T., & Yuan, G. (1996). PDES—An expert system for constructing the precedence diagram. Journal Of The Franklin Institute333(6), 975-990. doi: 10.1016/0016-0032(96)00037-3