After reviewing the Getta Byte Transcript (attached word document), write a 2 page paper on what Ima Payne, the Project manager at Getta Byte Software, put together for her preliminary project schedul

Transcript:


Getta Byte Software

The WBS and Schedule

Time to create a WBS for the the billing project.

Hmm...
What are the major tasks?

We decided to purchase BillRite software.

I know the milestones.

  • Finalize requirements

  • Purchase software

  • Customize software

  • Transfer data to cloud

  • Train personnel

  • Go live

I need to add detail or subtasks.

Finalize Requirements

  • Gather requirements from users.

  • Gather requirements from customers.

Purchase Software

  • Select vendor.

  • Negotiate contract.

  • Execute purchase.

Customize Software

  • Define features.

  • Set up test environment.

  • Develop customization.

  • Test customization.

Transfer data to cloud

  • Validate data.

  • Map fields.

  • Transfer data.

Train Personnel

  • Develop training with vendor.

  • Schedule training for CSRs.

  • Conduct training.

Go Live

  • Release system into production.

Well! Let's see what that looks like in a schedule.

Getta Byte Schedule

Wow! We have to get started so we can make the September 1 deadline.

Getta Byte Software

The End