n Assignment 1, you have defined key portions of your project. Now, it is time to develop a Work Breakdown Structure (WBS), and project schedule for your project. Note: Please use the project from Ass

Running head: project proposal: initiating and planning 0



Project Proposal:











Brief Summary

A wedding is one of the most significant and valuable events in the life of an individual. The wedding couples particularly aspire to make the day memorable forever. Most of the individuals hold a restricted budget to be spent on the wedding ceremony, but their expectations are high to make the event memorable for a long time. This project proposal is specific to the particular event for providing appropriate support to the couple to make their wedding day memorable. The project will ensure that there is proper arrangement for the event, and all the tasks are performed appropriately and are in line with the allocated budget (McKenna & Baume, 2015). The proposal will develop a plan for the wedding using a project management application.

Three Goals and Three Objectives of the Project

The goals of the wedding project include;

  • To complete containing all the activities as per the requirements of the couple.

  • To complete within the constraint of time, quality, and money.

  • To minimize potential risks coming in the middle to avoid any discrepancies during the event (Dowsett, Green, Sexton, & Harty, 2019).

The objectives of the project include;

  • To utilize all the allocated resources properly for ensuring the sequential execution of the activities.

  • To allocate roles and responsibilities to all the team members to avoid disagreement.

  • To develop and implement proper risk management (Guo, Yiu & Gonzalez, 2015).

Key Customers and Two Stakeholders of the Project

The key customers are the wedding couple; they will provide all the information expecting from the project to the project team. Moreover, they will be required to take an active part in the development of project scope, i.e., information about time, budget, quality, etc. (McKenna & Baume, 2015). At the time of project completion, the wedding couple will accept it.

The first key stakeholder of the project will be the families of the couple. They are the people who keep much interest in the event to make the wedding day of their relatives amazing. They also want to keep the event free of disruption to enjoy wholeheartedly. The second stakeholder will be the project team members. They will not only take an active part in the planning process but also carry out all the project activities efficiently. The proper communication, coordination, and technical expertise of the team members will add value to the project, ensuring the successful completion (Dowsett, Green, Sexton, & Harty, 2019).

Three Milestones of the Project

  • Complete Wedding arrangements

  • Complete the project within time-frame

  • Complete the project with quality and allocated budget

Timeline for the Project

Sr. No.

Tasks

Deadlines December 01, 2019

The arrival of Bride to the hair saloon

12:00

The arrival of Bride to church

12:15

The arrival of girls at church and sanctuary preparation

12:30

Video shoot of girls

12:45

Video shoot of boys

12:50

Preparation of bride for the ceremony

12:55

Beginning of ceremony

13:00

The arrival of Limo at the church

13:05

Greetings to guests arriving at the ceremony

13:10

10

Post ceremony video shoot

13:15

11

Post ceremony photoshoot

13:25

12

Slop time

13:30

13

Transportation of bridal to ceremony hall through Limo

13:40

14

Completion of reception hall preparations

13:45

15

Introduction of the bridal party

13:50

16

Toast

13:55

17

Serving of the dinner

14:10

18

Announcement of best wishes to the couple from DJ

14:20

19

Beginning of Videography

14:25

20

Best wishes speeches from the family members

14:30

21

Views sharing from the couple

14:40

22

Beginning of photography

14:45

23

Cake cutting

14:50

24

Garter toss

14:55

25

Bouquet toss

15:00

26

Videography of the love story

15:05

27

Dancing of the couple

15:10

28

Dancing of all the guests

15:15

29

Drinks

15:25

30

Closure

15:30

Estimation of Overall Cost of the Project

Staffing

Project Manager

$1,000

Wedding Planner

500

Team Lead

300

Waiter

100

Photographer

200

Videographer

200

DJ

200

Limo Driver

150

Total

$2,650

Non-Staffing

Music System

$250

Flower

150

Bride and groom dresses

500

Food

10,000

Drinks

5,000

Decoration Material

8,000

Projector

1,000

Makeup Stuff

2,000

First Aid Kit

1,000

Fragrance

200

Total

31,000

Grand Total

$32,650

Conclusion

The project management practices are critical for the successful completion of any project. The wedding project will be effectively completed for the client using the project management practices and above-developed plan.

References

Dowsett, R., Green, M., Sexton, M., & Harty, C. (2019). Projecting at the project level: MMC supply chain integration roadmap for small housebuilders. Construction Innovation19(2), 193–211. doi: 10.1108/ci-07-2017-0059

Guo, B., Yiu, T., & Gonzalez, V. (2015). A System Dynamics View of Safety Management in Small Construction Companies. Journal Of Construction Engineering And Project Management5(4), 1-6. doi: 10.6106/jcepm.2015.5.4.001

McKenna, A., & Baume, G. (2015). Complex project conceptualization and the linguistic turn; the case of a small Australian construction company. International Journal Of Project Management33(7), 1476-1483. doi: 10.1016/j.ijproman.2015.06.005