A project plan outlines recommended approaches on how to use the network, database management system, software, and cloud service technologies selected. Industry best practices dictate selection crite

Project Proposal Template

Instructions: Fill out each of the sections below with information relevant to your project, and add your company’s name.

Chase Bank

Project Proposal

Project Scope statement

Project Title:

Sales processes improvement of CHASE BANK

Project Sponsor(s):

CHASE BANK

Business Context for the System:

The organization needs an improved sales software application because the current one does not integrate with other systems and the organization revenue is low due to lack of proper report generation by the software so we cannot monitor and manage sales.

Project Scope Description:

Analyzing sales process of the organization, designing and programming a system that improves sales process, look for a cloud-based CRM solution, advice the best cloud-based CRM solution to the management of the organization.

Date Prepared:

29th March 2020

Prepared By:

Travis Lambert

Problems/Issues/opportunities the proposed system expected to Solve

Problems

Issues

Opportunities

  • Lack of integration of sales software and other system applications

  • Sales software application does not give reports and information to facilitate managing and monitoring of sales


  • Sales software application does not support sales cycle for service and product

  • Generation of more leads

  • Increase of sales

  • Improvement of customer services

  • Reduction of organization’s cost

  • Increase of organization’s revenue

  • Integration of sales software applications and other systems

project objectives

Project Objective Name

Project Objective Description

Cloud-based CRM At completion of the project we need to have a cloud-based solution CRM
Integration of system At completion of the project the sales software applications need to be integrated with other systems
Improvement of sales processes At completion of the project the organization sales processes need to improve


project deliverables

Project Deliverable Name

Project Deliverable Description

Cloud-based CRM Delivery of a cloud-based CRM
Sales software application Delivery of improved sales software application that also integrates with other systems and the improvement needs to bring about: low organizational cost, increased revenue, report generation to monitor and manage sales, increased sales, improved customer service




project acceptance criteria

Project Acceptance Criteria Name

Project Acceptance Criteria Description

Software integration testing The sales software application needs to be tested on whether it integrates with other systems
Software testing The sales software application needs to be tested on whether it works as required
Security testing The sales software application needs to be tested in terms of security, that is, can it be brought down on its knees by an attacker via the network or in-house
Network security testing The network needs to be tested for security issues because of the integration of the cloud-based CRM
project exclusions

Project Exclusion Name

Project Exclusion Description

Overall Security testing The project will not include overall security testing of the organization’s system such as workstations, bring your own device security testing etc. the only security testing that will be done will be how secure is the sales software application and the network security due to the host-based CRM
Implementation of the security of the cloud-based CRM The project will only test on how secure the cloud-based CRM is but will not implement the security measures if it is not that secure. We will only recommend to the cloud computing provider




project constraints

Project Constraint Name

Project Constraint Description

Communication The project manager is a busy person and the organization has a lot of branches globally, so it is hard to communicate with the project manager when he/she has travelled
Skills All our enterprise applications are built using Java programming language. It is time consuming and resource intensive in terms of finances to find highly skilled Java programmers who can work on such a complex application
Time Our application may keep changing in requirements hence the time of delivery of the project may keep changing.


project assumptions

Project Assumption Name

Project Assumption Description

Programming language We will assume that the programming language that will be used is Java programming language because all applications of the organization use it
Database management system We will assume that the database management system that will be used is Oracle because it is the one widely used within the organization




PROJECT METHODOLOGY

The project methodology that we will use for the project is agile methodology and this is because we need to involve the customer in the project making process and also due to the changing nature of requirements of our project (development of sales software application).

high-level work schedule: Project Scope

Description of Work

Assumptions and Constraints

The overall work entails delivery of sales software application that integrates with other systems and also incorporation of cloud-based CRM

Constraints include: communication, skills and time

Assumptions include: programming language and database management system used

Milestones

Due Dates

Analysis of the current sales software application

Gathering of requirements of the improved software application

Designing of wireframes of the improved software application

Conceptual and logical modeling of database

Physical designing of database

Programming of sales software application

Integration of sales software application with database

Integration of sales software application with other systems

Software testing

Integration testing

User acceptance testing

Integration of cloud-based CRM

Network testing

Two weeks - 1st April – 15th April 2020

1 week - 16th April – 23rd April 2020

2 weeks – 24th April – 8th May 2020

1 week – 9th May – 16th May 2020

2 weeks – 18th May – 1st June 2020

1 month – 1st June – 1st July 2020

2 weeks – 2nd July – 15th July 2020

2 weeks – 16th July – 29th July 2020

All testing :

1 month – 1st August – 31st August 2020

2 weeks – 1st September – 15th September 2020

2 weeks – 16thSeptember – 30th September 2020

ID

Activity

Resource

Labor

Hours

Labor

Rate

Labor

Total

Material

Units

Material

Cost

Material

Total

Total

Cost

Analysis of the current sales software application

Sales software application in place

80 hours

$40 per hour

$3200

None

None

None

$3200

Gathering of requirements of the improved software application

Pens,

Notebooks

40 hours

$5

$200

4 pens

1 notebook

$0.05

$0.50

$5.2

$205.2

Designing of wireframes of the improved software application

computers

80 hours

$60

$4800

2 computers

Adobe suite

$1000

$300

$2300

$8400

Conceptual and logical modeling and physical designing of database

Oracle database management system

120 hours

$55

$6600

Oracle database management system

$17,500

$17,500

$24,100

Programming, integration with database, and integration with other systems

Java

320 hours

$40

$12800

Java

None

None

$12800

All testing

Testing software (jUnit)

160 hours

$30

$4800

jUnit testing software

none

none

$4800

Quality Requirements

The software needs to comply with GDRP (EU General Data Protection Regulation)

Acceptance Criteria

The sales software application will be tested in terms of security, integration with other system and network testing needs be performed due to the integration of cloud-based CRM

Technical Information

The programming language that will be used is Java.

The software testing will be done with a software known as jUnit

The database to be used is Oracle database

Agreement Information

Every design, sketches, and the sales software application will be the product of the organization and as employees of the organization you will be required to sign a non-disclosure agreement as project team members