Project rollout begins after a project has been implemented, tested, and judged stable and functional enough to be moved into production. The project rollout process comprises of specific steps that m
University of Phoenix Material
Project Implementation Plan Example
Instructions: Replace the italicized information with information relevant to your project.
CHase Bank Implementation Phase Project Plan Task |
Activity Name |
Resource | Schedule Start Date | Schedule Finish Date | Schedule Comments |
Prepare for Implementation | Identify the implementation team | CIO / Project Sponsor | 6/4/2018 | 6/8/2018 | |
Order server hardware for production environment and test / QA environment | IT Manager / CIO | 6/4/2018 | 6/29/2018 | ||
Order client hardware for production environment and test / QA environment | IT Manager / CIO | 6/4/2018 | 6/29/2018 | ||
Order Cloud Computing Services and software subscriptions | IT Manager / CIO | 6/4/2018 | 6/29/2018 | ||
Obtain on premise software applications | IT Manager / CIO | 6/4/2018 | 6/29/2018 | ||
Create user ids and groups for on premise technology | System Admin | 7/2/2018 | 7/13/2018 | ||
Create security infrastructure for production and test / QA environment | System Admin | 7/2/2018 | 7/13/2018 | ||
Prepare Test Environment | Install test / QA servers and software | System Admin | 7/16/2018 | 7/20/2018 | |
Install test / QA client machines and software | System Admin | 7/16/2018 | 7/20/2018 | ||
Configure test / QA environment | System Admin | 7/16/2018 | 7/20/2018 | ||
Prepare Production Environment | Install production servers and software | System Admin | 7/23/2018 | 7/27/2018 | |
Install production client machines and software | System Admin | 7/23/2018 | 7/27/2018 | ||
Configure production environment / Integrate with Cloud Service architecture | System Admin | 7/23/2018 | 7/27/2018 | ||
Data Conversions | Perform data conversions and loading into the test / QA environment | Data Specialists | 7/13/2018 | 8/10/2018 | |
Perform data conversions and loading into the production environment | Data Specialists | 7/13/2018 | 8/10/2018 | ||
Documentation | Ensure all documentation applicable to implementation is available | Documentation Specialists / Technical Writers | 6/11/2018 | 8/17/2018 | |
Training | Provide administrator training | Trainers | 8/13/2018 | 8/17/2018 | |
Provide support training | Trainers | 8/13/2018 | 8/17/2018 | ||
Provide end-user training | Trainers | 8/13/2018 | 8/17/2018 | ||
Go-Live | Production Go-live | CIO / Project Sponsor | 8/27/2018 | 8/27/2018 |