Calculate the Production Overhead for the Administration Department. (5) Calculate the Production Overhead for the Maintenance Department. (6)Calculate the Production Overhead for Milling and Finishin

Dee Limited’s factory comprises of two production departments, Milling and Finishing, and two service departments Maintenance and Administration. The following estimated data are provided:

Production department

Service department

Milling

Finishing

Maintenance

Administration

Budgeted overheads

524 000

480 000

240 000

150 000

Machine hours

30 000

20 000

Area occupied (m²)

6 300

2 700

1 200

900

Number of employees

150

100

40

30

Note:

  • Administration department cost is allocated based on number of employees.

  • Maintenance department cost is allocated based on area occupied.

  • Production overheads are calculated based on machine hours.

Required:

    1. Calculate the Production Overhead for the Administration Department. (5)

    2. Calculate the Production Overhead for the Maintenance Department. (6)

    3. Calculate the Production Overhead for Milling and Finishing (separately) based on machine hours. (6)