*** Please utilize the Kanban project methodology : please look at Scenario B attachment*** Assignment 1: (please use the project proposal attachment) For this assignment, you will create a 3- to 4-

Project Implementation Plan Example

BSA/425 v1

Page 2 of 2

University of Phoenix Material

Project Implementation Plan Example

Instructions: Replace the italicized information with information relevant to your project.

YOUR PROJECT NAME Implementation Phase Project Plan

Task

Activity Name

Resource

Schedule Start Date

Schedule

Finish Date

Schedule Comments

Prepare for Implementation

Identify the implementation team

CIO / Project Sponsor

6/4/2018

6/8/2018

Order server hardware for production environment and test / QA environment

IT Manager / CIO

6/4/2018

6/29/2018

Order client hardware for production environment and test / QA environment

IT Manager / CIO

6/4/2018

6/29/2018

Order Cloud Computing Services and software subscriptions

IT Manager / CIO

6/4/2018

6/29/2018

Obtain on premise software applications

IT Manager / CIO

6/4/2018

6/29/2018

Create user ids and groups for on premise technology

System Admin

7/2/2018

7/13/2018

Create security infrastructure for production and test / QA environment

System Admin

7/2/2018

7/13/2018

Prepare Test Environment

Install test / QA servers and software

System Admin

7/16/2018

7/20/2018

Install test / QA client machines and software

System Admin

7/16/2018

7/20/2018

Configure test / QA environment

System Admin

7/16/2018

7/20/2018

Prepare Production Environment

Install production servers and software

System Admin

7/23/2018

7/27/2018

Install production client machines and software

System Admin

7/23/2018

7/27/2018

Configure production environment / Integrate with Cloud Service architecture

System Admin

7/23/2018

7/27/2018

Data Conversions

Perform data conversions and loading into the test / QA environment

Data Specialists

7/13/2018

8/10/2018

Perform data conversions and loading into the production environment

Data Specialists

7/13/2018

8/10/2018

Documentation

Ensure all documentation applicable to implementation is available

Documentation Specialists / Technical Writers

6/11/2018

8/17/2018

Training

Provide administrator training

Trainers

8/13/2018

8/17/2018

Provide support training

Trainers

8/13/2018

8/17/2018

Provide end-user training

Trainers

8/13/2018

8/17/2018

Go-Live

Production Go-live

CIO / Project Sponsor

8/27/2018

8/27/2018

Copyright © 2018 by University of Phoenix. All rights reserved.