Activity II: A project has 11 activities that can be accomplished either by one person working alone or by several people working together. The activities, precedence constraints, and time estimates a

Activity

Immediate predecessors

Person-days required

A

 

10

B

A

8

C

A

5

D

B

6

E

D

8

F

C

7

G

E,F

4

H

F

2

I

F

3

J

H,I

3

K

J,G

2