Activity II: A project has 11 activities that can be accomplished either by one person working alone or by several people working together. The activities, precedence constraints, and time estimates a
Activity | Immediate predecessors | Person-days required |
A |
| 10 |
B | A | 8 |
C | A | 5 |
D | B | 6 |
E | D | 8 |
F | C | 7 |
G | E,F | 4 |
H | F | 2 |
I | F | 3 |
J | H,I | 3 |
K | J,G | 2 |