Question 1 8 pts

The manager of a crew that installs carpeting has tracked the crew's output over the past several weeks, obtaining these figures:

Week

Crew Size

Yards Installed

96

72

92

50

69

52

Compute the labor productivity for each of the weeks.

Week 1:

Week 2:

Week 3:

Week 4:

Week 5:

Week 6:

 

Flag this Question

Question 2 2 pts

On the basis of your calculations, what can you conclude about crew size and productivity?

HTML Editor Keyboard Shortcuts

 

0 words

 

Flag this Question

Question 3 8 pts

Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars.  Assume 40-hour weeks and an hourly wage of $12.  Overhead is 1.5 times the weekly labor cost.  Material cost is $6 per pound.  Round your final answer to two decimal places.

Week

Output (units)

Workers

Material (lbs)

30,000

450

33,600

470

32,200

460

35,400

480

Week 1:

Week 2:

Week 3:

Week 4:

 

Flag this Question

Question 4 2 pts

What do the productivity figures suggest?

HTML Editor Keyboard Shortcuts

 

0 words

 

Flag this Question

Question 5 10 pts

An operation has a 10% scrap rate.  As a result 72 pieces per hour are produced.  What is the potential increase in labor productivity that could be achieved by eliminating the scrap?

Round your answer to one decimal place.

 

Flag this Question

Question 6 10 pts

The following table shows data on the average number of customers processed by several bank service units each day.  The hourly wage rate is $25, the overhead rate is 1.0 times labor cost, and material cost is $5 per customer.  

a.  Compute the labor productivity and the multifactor productivity for each unit.  Use an 8-hour day for multifactor productivity.

b.  Suppose a new, more standardized procedure is to be introduced that will enable each employee to process one additional customer per day.  compute the expected labor and multifactor productivity rates for each unit.

Round to two decimal places for the labor productivity rates.  Round to three decimal places for the multifactor productivity rates.

Unit

Employees

Customers Processed/Day

Labor Productivity

Multifactor Productivity

New Labor Productivity

New Multifactor Productivity

36

40

60

20