Assignment Content Project rollout begins after a project has been implemented, tested, and judged stable and functional enough to be moved into production. The project rollout process comprises of sp

BSA/425 Wk 5

Project Implementation Plan

Task

Activity Name

Resource

Schedule Start Date

Schedule

Finish Date

Schedule Comments

Prepare for Implementation

Identify the implementation team

CIO / Project Sponsor

6/4/2018

6/8/2018

Order server hardware for production environment and test / QA environment

IT Manager / CIO

6/4/2018

6/29/2018

Order client hardware for production environment and test / QA environment

IT Manager / CIO

6/4/2018

6/29/2018

Order Cloud Computing Services and software subscriptions

IT Manager / CIO

6/4/2018

6/29/2018

Obtain on premise software applications

IT Manager / CIO

6/4/2018

6/29/2018

Create user ids and groups for on premise technology

System Admin

7/2/2018

7/13/2018

Create security infrastructure for production and test / QA environment

System Admin

7/2/2018

7/13/2018

Prepare Test Environment

Install test / QA servers and software

System Admin

7/16/2018

7/20/2018

Install test / QA client machines and software

System Admin

7/16/2018

7/20/2018

Configure test / QA environment

System Admin

7/16/2018

7/20/2018

Prepare Production Environment

Install production servers and software

System Admin

7/23/2018

7/27/2018

Install production client machines and software

System Admin

7/23/2018

7/27/2018

Configure production environment / Integrate with Cloud Service architecture

System Admin

7/23/2018

7/27/2018

Data Conversions

Perform data conversions and loading into the test / QA environment

Data Specialists

7/13/2018

8/10/2018

Perform data conversions and loading into the production environment

Data Specialists

7/13/2018

8/10/2018

Documentation

Ensure all documentation applicable to implementation is available

Documentation Specialists / Technical Writers

6/11/2018

8/17/2018

Training

Provide administrator training

Trainers

8/13/2018

8/17/2018

Provide support training

Trainers

8/13/2018

8/17/2018

Provide end-user training

Trainers

8/13/2018

8/17/2018

Go-Live

Production Go-live

CIO / Project Sponsor

8/27/2018

8/27/2018