The Presentation Congratulations. Your project has been staffed and you are about to meet with the team for the first time. Initial impressions are important and you’ll need visuals for your presentat

To: Subject: Status Report Week 9 Last week we successfully established a team to train and roll out the new system, assigned team members' roles, and responsibilities and created a software implementation plan. Week 9 is a continuation of week 8, where we will launch system installation, conduct system configuration, set up the necessary outputs and reports, and test and run the outputs. This report's main objective is to provide feedback and status on the completion of week nine activities. The report will also identify the challenges encountered in the week and the activities for week ten. Project Task for this week:
  • System installation

  • System configuration

  • Setting up the necessary reports or outputs

  • Testing and running outputs

Project Task accomplished this week.
  • The system was launched successfully.

  • The system was configured.

  • The necessary reports and outputs were set up as planned.

  • The output was set and run as planned.

Project Issues
  • There was a delay in decision-making whenever a technical issue was experienced

  • We had to work extra time to deliver the project due to a tight work schedule

  • It was challenging to find the most effective software to support the configuration process, set the outputs, and run them accordingly

Project tasks planned for next week
    • Training of the staff on using the new system

    •  Conduct User Acceptance Testing (UAT)

    • Rewarding the implementation team