Q1) Why is it important to identify critical path and float time for your project? State one reason for both. (10 marks)

Q2) Use the below table and answer the questions associated with it. (50 marks)

Activity

Initial Node

Final Node

Estimated Duration

A

1

2

1

B

1

3

2

C

1

4

3

D

2

5

4

E

3

5

5

F

3

6

4

G

4

7

6

H

5

6

6

I

7

6

2

J

6

8

3



  1. Draw an AOA diagram. 5 marks

  2. Identify all paths in the network diagram with their durations. 5 marks

  3. What is the critical path for this project? 5 marks

  4. What is the earliest possible time to finish the project? 5 marks

  5. Find the slack time for each activity. 10 marks

  6. If task G was delayed by 1 days, how will this affect the project critical tasks and the project finish time? 5 marks

  7. If task H was delayed by 3 days, what will be the impact of that delay on the project finish time? 5 marks

  8. Use Project Plan 365 to produce the Gantt chart & network diagram of the project. 10 marks

Q3) Figure 2 shows the EVM data of a project. The budget is $100,000 and the project duration is of 10 months. It started on 1st Jan 2008. It is now 31st July and the table shown the actual cost (AC) and earned values (EV). Activity “Incorporate feedback” is 75% completed as today.

Figure 2: Earned Value Status of a 10-months project at July 31

Activity

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Plan project

2,000

2,000

 

 

 

 

 

 

 

 

Analyze requirements

 

3,000

7,000

 

 

 

 

 

 

 

Develop Data Model

 

 

3,000

3,000

 

 

 

 

 

 

Design database

 

 

 

6,000

6,000

 

 

 

 

 

Design forms &reports

 

 

 

 

4,000

12,000

 

 

 

 

Construct prototype

 

 

 

 

 

10,000

 

 

 

Test/evaluate prototype

 

 

 

 

 

4,000

6,000

 

Incorporate feedback

 

 

 

 

 

 

4,000

Test system

 

 

 

 

 

 

 

10,000 

9,000

9,000

Monthly AC

2,000

6,000

8,000

9,000

13,000

21,000

10,000

 

 

 

Monthly EV

2,000

6,000

9,000

9,000

14,000

22,000

 

 

 

  1. What is the Earned Value (EV) in July? 5 marks

  2. What is the Cumulative Earned Value (EV) as of 31st July 2008 5 marks

  3. What is the Cumulative Actual Cost (AC) as of 31st July 2008 5 marks

  4. What is the Cumulative Planned Value (PV) as of 31st July 2008 5 marks

  5. Calculate the Cost Variance (CV) as of 31st July 2008. 5 marks

  6. Calculate the Schedule Variance (SV) as of 31st July 2008. 5 marks

  7. What is the predicted total cost of the project when the project finishes. 5 marks

  8. What is the predicted finish date of the project. 5 marks

  9. Discuss the advantages and disadvantages of this technique (one of each). 5 marks