Draw the two ERD diagrams (name them) for the following :
The user is a director of research for a large foundation. Approximately three hundred facilities are staffed by the foundation’s twelve-hundred employees. Over seventeen-hundred projects are currently underway, with some three-hundred and fifty waiting to be worked on in the future.
Number each component (i.e. entities, relationships) in ERD 2 and identify which components are needed to report on the following (e.g. report 1 needs components 4, 5,7 to be produced):
List all current employees in name sequence |
|
List all employees who work at a particular facility |
|
Determine which facility has the most employees |
|
Display the names of all employees working on a project |
|
Display all the projects on which an employee is working |
|
List inactive (no employee assigned) projects |
|
Determine ratio of active to inactive projects
|
|
For the following tasks
Task | Duration | Predecessor | Successor | Constraints |
B overlaps A by 3 days | ||||
12 | D,G | |||
3 days take place between G | ||||
ending and H beginning | ||||
F,H | ||||
Draw the Network Chart – include task id, duration, ES, EF, LS, LF, slack
What is the critical path? What is slack time for tasks F and G?
Would the management of the project change if there was determined to be a new task H1 predecessor H successor I with duration 2? Why or Why not?
Would the management of the project change if there was determined to be a new task H1 predecessor H successor I with duration 5? Why or why not?
What is slack time and lag time?
Can the critical path of a project change? Why or why not?