check the file for question

  1. Draw the two ERD diagrams (name them) for the following :

The user is a director of research for a large foundation. Approximately three hundred facilities are staffed by the foundation’s twelve-hundred employees. Over seventeen-hundred projects are currently underway, with some three-hundred and fifty waiting to be worked on in the future.

Number each component (i.e. entities, relationships) in ERD 2 and identify which components are needed to report on the following (e.g. report 1 needs components 4, 5,7 to be produced):

List all current employees in name sequence

List all employees who work at a particular facility

Determine which facility has the most employees

Display the names of all employees working on a project

Display all the projects on which an employee is working

List inactive (no employee assigned) projects

Determine ratio of active to inactive projects

  1. ERD 1:

  2. ERD 2:

  1. For the following tasks

Task

Duration

Predecessor

Successor

Constraints

B overlaps A by 3 days

12

D,G

3 days take place between G

ending and H beginning

F,H

    1. Draw the Network Chart – include task id, duration, ES, EF, LS, LF, slack

    2. What is the critical path? What is slack time for tasks F and G?

    1. Would the management of the project change if there was determined to be a new task H1 predecessor H successor I with duration 2? Why or Why not?

    2. Would the management of the project change if there was determined to be a new task H1 predecessor H successor I with duration 5? Why or why not?

    3. What is slack time and lag time?

    4. Can the critical path of a project change? Why or why not?