For the following tasks
Task | Duration | Predecessor | Successor | Constraints |
B overlaps A by 3 days | ||||
12 | D,G | |||
3 days take place between G | ||||
ending and H beginning | ||||
F,H | ||||
Draw the Network Chart – include task id, duration, ES, EF, LS, LF, slack
What is the critical path? What is slack time for tasks F and G?
Would the management of the project change if there was determined to be a new task H1 predecessor H successor I with duration 2? Why or Why not?
Would the management of the project change if there was determined to be a new task H1 predecessor H successor I with duration 5? Why or why not?
What is slack time and lag time?
Can the critical path of a project change? Why or why not?