Eastern MAS Expansion Part 2: The Project In your PowerPoint presentation, please focus on the following: a. SWOT analysis b. Supplier evaluation c. Gant diagrams d. Activities chart plus crashing act
Eastern MAS Expansion Case Part 1
PROJECT DOCUMENT
Project Title | Eastern Mass Expansion | Ownership &Approval | Matt Ken | |
Project Start Date | March 14, 2023 | Project End Date | March 13, 2028 | |
Project description | ||||
Eastern Mass expansion (EME) aim to growth the business by evaluating market expansion into new geographic region. The forecast for East of Mississippi demand is 7.6 million (62%) increase over existing market. To stay completive, EME will seek to increase its capacity, add potential districts and new plant. | ||||
Business need | ||||
With the experience in the Western region, there is a great opportunity for business growth and implementing sustainable supply chain. | ||||
Project Strategy | ||||
Our strategy is to increase the sale by 50% the next five years. reducing velocity through supply chain, increase customer satisfaction. The actual system does not enable the process. The new expansion will increase the fill rate, production capacity. | ||||
Project Scope | ||||
Productivity, sale growth, supply chain integration, customer experience, and comparative advantage | ||||
Project Risk | ||||
Uncertainty logistics systems, managing project asset, failure of suppliers, adverse public opinion, poor leadership, inadequate tracking system, unrealistic schedules, natural disaster, legal ®ulations. Stakeholders’ analysis is imperative to mitigate risk. | ||||
Expected Sale | Year 1=40,000,000 Year 2=43,000,000 Year 3= 45,000,000 Year 4=60,000,000 Year 5= 71,000,000 | Benefits Types |
| |
Deliverables |
| Options considered | 1.Year1 Western MAS 2.Ad new DCs 3.Add new Plant in Y3 | |
Assumptions |
| |||
Expected Profit Margin | Year 5= 30% | |||
Estimation Costs | $18,000,000 | |||
Project Team | 1 Project Managers, 1 District Manager, 1 network designer | |||
Tentative Schedule | Key milestone | Expected time(days) | Preceding Activities | |
A. Develop the project charter | ||||
B. Analysis Stakeholders | 30 | |||
C. Set up procedures | 45 | |||
D. Analyze market opportunity | 60 | C | ||
E. Evaluate suppliers | 90 | D, C | ||
F. Implement supply chain Performance | 180 | |||
G. Comparative analysis | 90 | D, F | ||
H. Risks Management | 120 | |||
I. Monitoring &Evaluations | 90 | H, F |