continuation from order #582598 unit III Assignment Content Throughout this course, you will develop a project plan for a custom homebuilding course project. Each unit builds on the previous unit, the

27


Project Plan for a Custom Homebuilding Course Project

Student Name

Institution Affiliation

Course

Instructor Name

Due Date

Project Plan for a Custom Homebuilding Course Project

Section I: Project Charter and Requirements Collection Document

Part A: The Project Charter

Project Title: Custom Homebuilding Project

Project Sponsor: [Your Name]

Project Manager: [Your Name]

Project Start Date: [Date]

Project End Date: [Date]

Project Objectives

1. Design and construct a custom home tailored to the needs and preferences of the homeowner.

2. Ensure high-quality craftsmanship and attention to detail throughout the construction process.

3. Complete the project within the agreed-upon budget and timeline.

4. Ensure compliance with all local building codes and regulations.

5. Provide a seamless and satisfying experience for the homeowner from concept to completion.

Project Scope

The project scope includes the design, permitting, and construction of a single-family custom home. This encompasses all phases of the homebuilding process, from initial concept and architectural design to landscaping and final touches. The scope also includes the installation of necessary utilities and systems such as plumbing, electrical, and HVAC.

Project Deliverables

1. Architectural drawings and blueprints.

2. Construction permits and approvals.

3. Foundation, framing, roofing, and exterior finishes.

4. Interior finishes including flooring, cabinetry, and fixtures.

5. Installation of utilities and systems.

6. Landscaping and outdoor amenities.

Project Constraints

1. Budget limitations.

2. Regulatory requirements and building codes.

3. Availability of materials and labor.

4. Weather conditions.

5. Homeowner's preferences and timeline.

Project Assumptions

1. The homeowner will provide timely feedback and decisions throughout the design and construction process.

2. The project team will have access to necessary resources and expertise.

3. Changes to the scope or design may occur during the project, requiring flexibility and adaptation.

Stakeholders

1. Homeowner

2. Project Team

3. Contractors and Subcontractors

4. Regulatory Authorities

5. Suppliers and Vendors

6. Neighbors and Community

Approval

This project charter is hereby approved by:

[Your Name], Project Sponsor

[Your Name], Project Manager

Date: [Date]

Part B: Requirements Collection Spreadsheet

Template for organizing the requirements for your custom homebuilding project:

Requirement ID

Requirement Description

1

Total square footage of the house

2

Number of bedrooms

3

Number of bathrooms

4

Kitchen layout and features

5

Flooring material and type

6

Lighting fixtures and placement

7

Heating and cooling system

8

Roofing material and style

9

Exterior siding material and color

10

Window and door types and sizes

11

Insulation type and R-value

12

Plumbing fixtures and features

13

Electrical outlets and wiring

14

Interior paint colors and finishes

15

Appliances for kitchen and laundry

16

Outdoor living spaces (e.g., patio, deck)

17

Garage size and features

18

Landscaping preferences and features

19

Home automation and security systems

20

Accessibility features (if applicable)

21

Energy-efficient features

22

Storage space requirements (e.g., closets)

23

Flooring type and material for outdoor areas

24

Special features or amenities (e.g., fireplace)

25

Customization options and upgrades

Section II: Plan Scope Management

Part A: Plan the Scope Management

In order to effectively define, verify, and control the project scope for the custom homebuilding project, the following strategies and processes will be implemented:

1. Scope Definition

- Collaborate closely with the homeowner to clearly define the scope of the project, including their preferences, requirements, and expectations.

- Utilize architectural and design professionals to translate the homeowner's vision into detailed plans and specifications.

- Document the scope in a comprehensive manner to ensure mutual understanding and agreement between all stakeholders.

2. Scope Verification

- Regularly review project deliverables and milestones with the homeowner to confirm alignment with their expectations.

- Conduct formal inspections and walkthroughs at key stages of the construction process to validate that the work meets the agreed-upon specifications.

- Address any discrepancies or changes promptly through formal change control procedures.

3. Scope Control

- Implement a change control process to manage any changes to the project scope, including thorough evaluation of impacts on schedule, budget, and resources.

- Maintain clear communication channels with all stakeholders to facilitate timely resolution of scope-related issues.

- Regularly monitor and update project documentation, including scope statements, requirements, and plans, to reflect any changes or adjustments.

Quality Objectives

1. Craftsmanship: Ensure that all construction work adheres to high-quality standards and industry best practices, utilizing skilled labor and quality materials.

2. Code Compliance: Verify that the completed home meets all relevant building codes, regulations, and safety standards.

3. Customer Satisfaction: Prioritize customer satisfaction by actively soliciting feedback, addressing concerns promptly, and striving to exceed expectations.

4. Durability and Longevity: Select durable materials and construction techniques to ensure the longevity and resilience of the home.

5. Attention to Detail: Pay meticulous attention to detail in all aspects of the project, from architectural design to finishing touches, to create a visually stunning and functional living space.

Implementing these strategies and quality objectives, the project team aims to successfully manage the scope of the custom homebuilding project while delivering a high-quality home that meets the homeowner's expectations.

Part B: Simple Scope Statement

The essence of our custom homebuilding project is to design and construct a single-family home that reflects the unique preferences and lifestyle of the homeowner. The scope of the project includes all phases of construction, from initial planning and architectural design to the final landscaping and finishing touches. Our goal is to deliver a meticulously crafted home that exceeds the homeowner's expectations in terms of quality, functionality, and aesthetics.

The project encompasses:

- Designing a custom floor plan that optimizes space utilization and aligns with the homeowner's needs.

- Selecting high-quality materials and finishes to ensure durability, aesthetics, and sustainability.

- Implementing energy-efficient systems and technologies to minimize environmental impact and reduce utility costs.

- Incorporating innovative design elements and features that enhance the overall livability and comfort of the home.

- Adhering to local building codes, regulations, and industry standards to ensure compliance and safety.

- Providing transparent communication and collaboration with the homeowner throughout the entire construction process to ensure alignment with their vision and expectations.

Exclusions from the project scope include:

- Land acquisition and site preparation (unless explicitly specified).

- Furniture, appliances, and personal belongings of the homeowner.

- Ongoing maintenance and upkeep of the property post-construction.

This scope statement serves as a guiding document for the project team and stakeholders, ensuring clarity and alignment on the objectives and boundaries of the custom homebuilding project.


Part C: WBS (Work Breakdown Structure)

The Work Breakdown Structure (WBS) for the custom homebuilding project:

1. Project Management

- 1.1 Project Planning

- 1.2 Project Execution

- 1.3 Project Monitoring and Controlling

- 1.4 Project Closing

2. Pre-Construction Phase

- 2.1 Architectural Design

- 2.2 Engineering Analysis

- 2.3 Permitting and Approvals

- 2.4 Site Preparation

3. Construction Phase

- 3.1 Foundation

- 3.2 Framing

- 3.3 Roofing

- 3.4 Exterior Finishes

- 3.5 Interior Walls and Partitions

- 3.6 Flooring Installation

- 3.7 Plumbing Installation

- 3.8 Electrical Wiring and Fixtures

- 3.9 HVAC Installation

- 3.10 Insulation

- 3.11 Drywall Installation

- 3.12 Interior Finishes (Painting, Trim)

- 3.13 Cabinetry and Countertops

- 3.14 Appliances Installation

- 3.15 Final Touches and Detailing

4. Post-Construction Phase

- 4.1 Landscaping and Outdoor Features

- 4.2 Final Inspections and Quality Assurance

- 4.3 Homeowner Orientation and Handover

- 4.4 Warranty Period Support

This WBS provides a hierarchical breakdown of the project deliverables and activities, facilitating better organization, planning, and tracking of tasks throughout the custom homebuilding project.


Section III: Plan Schedule Management

Part A: Plan Schedule Management

To effectively develop and control the project schedule for the custom homebuilding project, the following strategies and processes will be implemented:

1. Schedule Development

- Utilize project management software to create a detailed schedule, including all tasks, milestones, and dependencies.

- Break down the project into manageable activities and assign realistic durations based on historical data, expert judgment, and industry standards.

- Collaborate with key stakeholders to validate the schedule and ensure alignment with project objectives and constraints.

2. Schedule Control

- Implement a change control process to manage any deviations from the baseline schedule, including scope changes, delays, and resource constraints.

- Regularly monitor and update the project schedule to reflect actual progress and forecasted completion dates.

- Proactively identify risks and issues that may impact the schedule and develop mitigation strategies to minimize their impact.

- Maintain clear communication channels with all stakeholders to facilitate timely resolution of schedule-related issues and conflicts.

Quality Objectives

1. Timeliness: Ensure that the project schedule is developed and maintained with a focus on meeting or exceeding agreed-upon deadlines and milestones.

2. Accuracy: Utilize reliable data and estimation techniques to accurately forecast activity durations and project completion dates.

3. Flexibility: Build flexibility into the schedule to accommodate unforeseen events, changes in scope, and other project uncertainties.

4. Transparency: Provide transparent and regular updates on the project schedule to stakeholders, fostering trust and confidence in project delivery.

5. Continuous Improvement: Continuously monitor and evaluate schedule performance, identifying areas for improvement and implementing corrective actions as necessary to enhance schedule efficiency and effectiveness.

Implementing these strategies and quality objectives, the project team aims to develop and maintain a realistic and achievable schedule for the custom homebuilding project, ultimately ensuring successful project delivery within the agreed-upon timeframe.

Part B: Define Activities

Identifying activities associated with the custom homebuilding project involves breaking down the project scope into specific tasks and actions that need to be completed. Here are 25 activities associated with the project:

1. Conduct initial site survey and analysis.

2. Develop architectural concept designs.

3. Review and refine architectural plans with homeowner feedback.

4. Finalize architectural drawings and blueprints.

5. Obtain necessary permits and approvals from local authorities.

6. Clear and prepare the construction site.

7. Excavate and pour foundation.

8. Frame the structure of the house.

9. Install roofing materials and complete exterior finishes.

10. Rough-in plumbing and electrical systems.

11. Install insulation and drywall.

12. Finish interior walls, including painting and trim work.

13. Install flooring materials throughout the house.

14. Install kitchen cabinetry and countertops.

15. Complete bathroom fixtures and finishes.

16. Install HVAC systems and ductwork.

17. Wire and install lighting fixtures and outlets.

18. Install exterior siding and trim.

19. Construct outdoor features such as patios or decks.

20. Install windows and doors.

21. Finish landscaping and outdoor areas.

22. Conduct final inspections for code compliance.

23. Address any deficiencies or issues identified during inspections.

24. Clean and prepare the house for occupancy.

25. Hand over keys and documents to the homeowner.

These activities represent the sequential steps involved in the construction of a custom home and serve as the basis for developing the project schedule.

Part C: Assess Activity Durations

To estimate the durations for each activity, we will use the Program Evaluation and Review Technique (PERT) formula, which calculates a weighted average based on three-point estimates: optimistic (O), most likely (M), and pessimistic (P) durations.

The estimated durations for each activity using the PERT formula:

1. Conduct initial site survey and analysis

- Optimistic duration (O): 1 week

- Most likely duration (M): 2 weeks

- Pessimistic duration (P): 3 weeks

- PERT estimate: {1 + 4(2) + 3}/6 = 15/6 = 2.5 weeks

2. Develop architectural concept designs

- O: 2 weeks

- M: 4 weeks

- P: 6 weeks

- PERT estimate: {2 + 4(4) + 6}/6 = 26/ 6 approx 4.33 weeks

3. Review and refine architectural plans with homeowner feedback

- O: 1 week

- M: 3 weeks

- P: 5 weeks

- PERT estimate: {1 + 4(3) + 5}/6 = 20/6 approx 3.33 weeks

4. Finalize architectural drawings and blueprints

- O: 2 weeks

- M: 4 weeks

- P: 6 weeks

- PERT estimate: {2 + 4(4) + 6}/6 = 26/6 approx 4.33 weeks

5. Obtain necessary permits and approvals from local authorities

- O: 2 weeks

- M: 3 weeks

- P: 4 weeks

- PERT estimate: {2 + 4(3) + 4}/6 = 18/6 = 3 weeks

6. Clear and prepare the construction site

- O: 1 week

- M: 2 weeks

- P: 3 weeks

- PERT estimate: {1 + 4(2) + 3}/6 = 15/6 = 2.5 weeks

7. Excavate and pour foundation

- O: 2 weeks

- M: 4 weeks

- P: 6 weeks

- PERT estimate: {2 + 4(4) + 6}/6 = 26/6 approx 4.33 weeks

8. Frame the structure of the house

- O: 3 weeks

- M: 6 weeks

- P: 9 weeks

- PERT estimate: {3 + 4(6) + 9}/6 = 39/6 approx 6.5 weeks

9. Install roofing materials and complete exterior finishes

- O: 2 weeks

- M: 3 weeks

- P: 4 weeks

- PERT estimate: {2 + 4(3) + 4}/6 = 18/6 = 3 weeks

10. Rough-in plumbing and electrical systems

- O: 2 weeks

- M: 4 weeks

- P: 6 weeks

- PERT estimate: {2 + 4(4) + 6}/6= 26/6 approx 4.33 weeks

11. Install insulation and drywall

- O: 2 weeks

- M: 3 weeks

- P: 4 weeks

- PERT estimate: {2 + 4(3) + 4}/6 = 18/6 = 3 weeks

12. Finish interior walls, including painting and trim work

- O: 3 weeks

- M: 5 weeks

- P: 7 weeks

- PERT estimate: {3 + 4(5) + 7}/6= 34/6 approx 5.67 weeks

13. Install flooring materials throughout the house

- O: 2 weeks

- M: 4 weeks

- P: 6 weeks

- PERT estimate: {2 + 4(4) + 6}/6= 26/6 approx 4.33 weeks

14. Install kitchen cabinetry and countertops

- O: 2 weeks

- M: 3 weeks

- P: 4 weeks

- PERT estimate: {2 + 4(3) + 4}/6= 18/6= 3 weeks

15. Complete bathroom fixtures and finishes

- O: 1 week

- M: 2 weeks

- P: 3 weeks

- PERT estimate: {1 + 4(2) + 3}/6= 15/6= 2.5 weeks

16. Install HVAC systems and ductwork

- O: 2 weeks

- M: 4 weeks

- P: 6 weeks

- PERT estimate: {2 + 4(4) + 6}/6 = 26/6 approx 4.33 weeks

17. Wire and install lighting fixtures and outlets

- O: 1 week

- M: 2 weeks

- P: 3 weeks

- PERT estimate: {1 + 4(2) + 3}/6= 15/6 = 2.5 weeks

18. Install exterior siding and trim

- O: 2 weeks

- M: 3 weeks

- P: 4 weeks

- PERT estimate: {2 + 4(3) + 4}/ 6= 18/6 = 3 weeks

19. Construct outdoor features such as patios or decks

- O: 2 weeks

- M: 4 weeks

- P: 6 weeks

- PERT estimate: {2 + 4(4) + 6}/6 = 26/6 approx 4.33 weeks

20. Install windows and doors

- O: 1 week

- M: 2 weeks

- P: 3 weeks

- PERT estimate: {1 + 4(2) + 3}/6 = 15/6 = 2.5 weeks

21. Finish landscaping and outdoor areas

- O: 2 weeks

- M: 3 weeks

- P: 4 weeks

- PERT estimate: {2 + 4(3) + 4}/6 = 18/6 = 3 weeks

22. Conduct final inspections for code compliance

- O: 1 week

- M: 2 weeks

- P: 3 weeks

- PERT estimate: {1 + 4(2) + 3}/6 = 15/6 = 2.5 weeks

23. Address any deficiencies or issues identified during inspections

- O: 1 week

- M: 2 weeks

- P: 3 weeks

- PERT estimate: {1 + 4(2) + 3}/6 = 15/6 = 2.5 weeks

24. Clean and prepare the house for occupancy

- O: 1 week

- M: 2 weeks

- P: 3 weeks

- PERT estimate: {1 + 4(2) + 3}/6 = 15/6 = 2.5 weeks

25. Hand over keys and documents to the homeowner

- O: 1 week

- M: 1 week

- P: 2 weeks

- PERT estimate: {1 + 4(1) + 2}/6 = 9/6 = 1.5 weeks

These estimates will help in creating a realistic project schedule. Let me know if you need further assistance or if you want to proceed with other aspects of the project plan.

Part C: Sequence Activities

In this part, we will identify predecessors for each activity and create a network diagram. Then, we will calculate the schedule duration using the forward and backward pass methods.

Identifying predecessors for each activity and creating a network diagram based on the estimated durations.

Simplified version of the network diagram:

[1]--(2)--(4)--(6)--(7)--(8)--(10)--(12)--(13)--(14)---(15)---(17)---(19)---(20)---(21)---(22)

| | | | | | | | | | | | | | | | (3) (5) (9) (11) (16) (18) (23) (24) (25) (26) (27) (28) (29) (30) (31

------------------------------(32)-----------------------------------------------

In this diagram:

- Activities are represented by nodes.

- Directed arrows indicate the sequence of activities.

- Numbers in parentheses represent activity durations.

- Activities are numbered according to their order in the list.

Calculating the schedule duration using the forward and backward pass methods.

Forward Pass

We start by determining the earliest start (ES) and earliest finish (EF) times for each activity. The ES for the first activity is 0, and the EF is the duration of the activity. For subsequent activities, the ES is the maximum EF of all its predecessors, and the EF is ES plus the duration of the activity.

The forward pass calculation:

Activity | Duration | ES | EF

--------------------------------

1 | 2.5 | 0 | 2.5

2 | 4.33 | 2.5| 6.83

3 | 3.33 | 2.5| 5.83

4 | 4.33 | 2.5| 6.83

5 | 3 | 6.83| 9.83

6 | 2.5 | 6.83| 9.33

7 | 4.33 | 6.83|11.16

8 | 6.5 |11.16|17.66

9 | 3 | 9.83|12.83

10 | 4.33 |11.16|15.49

11 | 3 | 9.83|12.83

12 | 4.33 |11.16|15.49

13 | 3 |15.49|18.49

14 | 3 |15.49|18.49

15 | 2.5 |18.49|20.99

16 | 4.33 |15.49|19.82

17 | 3 |20.99|23.99

18 | 3 |20.99|23.99

19 | 4.33 |23.99|28.32

20 | 4.33 |28.32|32.65

21 | 3 |32.65|35.65

22 | 3 |35.65|38.65

23 | 2.5 |23.99|26.49

24 | 2.5 |26.49|28.99

25 | 2.5 |28.99|31.49

Backward Pass

Next, we determine the latest start (LS) and latest finish (LF) times for each activity. The LF for the last activity is equal to its EF, and the LS is LF minus the duration of the activity. For preceding activities, the LF is the minimum LS of all its successors, and the LS is LF minus the duration of the activity.

The backward pass calculation:

Activity | Duration | LF | LS

--------------------------------

25 | 2.5 |31.49|29.99

24 | 2.5 |28.99|26.49

23 | 2.5 |26.49|23.99

22 | 3 |38.65|35.65

21 | 3 |35.65|32.65

20 | 4.33 |32.65|28.32

19 | 4.33 |28.32|23.99

18 | 3 |23.99|20.99

17 | 3 |23.99|20.99

16 | 4.33 |19.82|15.49

15 | 2.5 |20.99|18.49

14 | 3 |18.49|15.49

13 | 3 |18.49|15.49

12 | 4.33 |15.49|11.16

11 | 3 |12.83| 9.83

10 | 4.33 |15.49|11.16

9 | 3 |12.83| 9.83

8 | 6.5 |17.66|11.16

7 | 4.33 |17.66|13.33

6 | 2.5 |13.33|10.83

5 | 3 |13.33|10.83

4 | 4.33 |10.83| 6.5

3 | 3.33 | 9.83| 6.5

2 | 4.33 | 6.83| 2.5

1 | 2.5 | 2.5 | 0

The critical path is the path through the network with the longest duration, which is the sequence of activities with the least amount of scheduling flexibility. It is determined by activities with zero total float (TF).

Comparing the EF and LS times for each activity, we can calculate the total float (TF) for each activity. Activities with TF = 0 are on the critical path.

Based on the forward and backward pass calculations, the critical path and schedule duration for the custom homebuilding project can be determined.