Project Management HW

MS Project Assignment #1.

A Project has the following tasks, the precedence relationships for the tasks and the expected duration of each task.

  1. Use MS Project software to prepare a Gantt chart for the project. The Gantt chart should display the name of the task, and the amount of slack for the task on each bar. Print your diagram and attach it as a pdf document to the rest of your answers for this assignment.

  2. Use MS Project to prepare a network diagram for the project. The diagram should fit only one page and should include a legend. Print your diagram and attach it as a pdf document to the rest of your answers for this assignment.

  3. Print from MS Project a diagram that shows the expected duration of this project.



Task

Predecessor

Duration (Weeks)

A- Product Rationale

12

B-Dev. Formula

C-Product Specification

3

D-Reg. Document

3

E- Dev. Pkg. Concept

4

F- Design packaging

6

G- Dev. Proc. System

C, D

6

H - Dev. Pkg. System

8

I- Study Facility Reqmts.

G, H

4

J- Capital Equipment list

3

K- Procure Process Eqpt.

16

L- Procure Packaging Eqpt

8

M- Procure Facilities

4

N- Install Process Eqpt

6

O- Install Packaging Eqpt

4

P- Install Facilities

4

Q - Written Procedures 1

G,H

7

Q’ Written Procedures 2

P,Q

3

R- Pilot Test

N,O, Q’

5


  1. Fill in the answers for the following tasks

Task

Total Slack