Comprehensive AAP (Implementation Section)
Project Schedule
| Date Completed | Project Milestone |
| July 2nd | Business requirements and network design requirements completed |
| July 9th | The draft of the network design, scope of work, equipment list, IP scheme, high level diagram, VoIP design, voice bandwidth, and wireless design |
| July 23rd | Requests for network design modification received from WWTC |
| July 23rd | The draft of the business security needs, security policies, security design, role of devices, and security diagram |
| July 30th | Requests for security design modification received from WWTC |
| July 30th | The draft of the business Active Directory needs, Active Directory features, creation of a forest, link New York site to HQ, creation of OUs, add users to OUs, creation of groups, creation of a GPO, and implementation of GPO policies |
| August 13th | Requests for Active Directory design modification received from WWTC |
| August 13th | The draft of the project implementation plan |
| August 20th | Requests for project implementation plan modification received from WWTC |
| August 20th | The final network design and implementation plan is submitted to WWTC |
| August 27th | Purchase of all required hardware and software is completed |
| September 11th | All required hardware and software is received |
| September 25th | All networking devices for the unclassified network are configured, put in place, and connected |
| September 29th | Connectivity testing completed for unclassified network devices |
| October 13th | Unclassified Security devices configured, put in place, and connected |
| October 20th | Security testing completed |
| November 3rd | Unclassified Servers installed and connected |
| November 10th | Server functionality testing |
| November 24th | All unclassified endpoint systems i.e. desktops, VoIP phones, and printers are configured and put in place on the unclassified network |
| December 4th | Active Directory is implemented on the unclassified network |
| December 8th | Testing completed for Active Directory and endpoints |
| December 18th | Unclassified VoIP is implemented; ISP and PSTN connections contracted |
| December 22nd | Internal testing completed for Wireless and VoIP |
| January 8th | Testing completed for ISP connectivity on the unclassified network; External testing completed for VoIP on the unclassified network |
| January 12th | Unclassified VPN connection to HQ is established |
| January 15th | Connectivity testing completed for the VPN connection to HQ |
| January 19th | All classified network devices are configured, put in place, and connected |
| January 26th | Connectivity testing completed for network devices |
| February 9th | All classified security devices are configured, put in place, and connected |
| February 14th | Security testing completed |
| February 21st | All classified servers are configured, put in place, and connected |
| February 26th | Server connectivity testing completed |
| March 2nd | All classified end user laptops are configured and put in place |
| March 7th | Connectivity testing completed for all end user laptops |
| March 9th | Classified connection with HQ is established |
| March 13th | Connectivity testing completed with HQ; all hardware and software are backed up |
| March 19th | All network documentation has been updated with any changes |
| April 30th | All WWTC administrators are trained |
| April 30th | All WWTC user accounts are created |
| May 5th | Validation testing completed for all WWTC user accounts |
| May 30th | Acceptability testing completed by WWTC |
| May 30th | The project is completed |