Project Charter – Implementation of Keller Students Information System

Implementation of Keller Students Information System


Project Charter

Version: 1.0



© Eric Dayal


Revision History

Role

Name

Signature

Date

Project Managers

Lompri Koroma, Tianye Lin,Maodo Sow, Nikhil Vasani

07/22/2017

Project Sponsor

Edkins, Ivonna

07/22/2017

Executive Sponsor

May, Vicki

07/22/2017

Date

Name

Comments

Version

07/22/2017

Devry New SIS

Establishment of new Student IS

1.0

05/31/2017

My Devry SIS

Current Keller SIS

Convas


Project Charter Approvals

Project managers:

_________X_________________

Project Sponsor:

_________X__________________

Executive Sponsor:

__________X________________

  1. About the Project Charter

1.1 Project Authorization

The intended upgrade of the existing computerized program will tremendously benefit Keller College. The main objective is to improve the efficacy of the system with regard to financial transparency, online registration of students as well as keeping and maintaining of crucial academic records of the students. With the success of the of charter projects, the process of online registration will be must faster and efficient. Similarly, the students will be able to conveniently monitor their academic progress online plus restoration of their confidence in the financial statements of their tuition fee estimations due to improved financial transparency. The main challenge with the proposed upgrade is the Network Access Control (NAC) related issues and the possibility of hacking. However, these challenges can be mitigated through the installation of preventive programs like firewall installation.

1.2 Audience

The intended audience for the charter project includes; IT experts at Keller College, various departments with the institution, students as well as College administrators. IT experts have a special role in the rolling out of the project as well as the pilot phase of the project. They ensure the success of the program through identification of possible failures and coming up with viable solutions geared towards making the intended upgrade successful. Other groups of the audience may play critical roles through their valuable suggestions and timely feedback on the impact on the upgrade program. Other indirect stakeholders include the government which may want to inject more resources to ensure the success of IT infrastructure improvements.

  1. Project Overview

2.1 Executive Summary

Keller College is one of the notable collegesin New York City, established a century ago. The institution has experienced tremendous growth over the decades, making the traditional system of conducting academic programs irresponsive to such growth in the population of the students. There have been concerted efforts geared towards the managing the explosion in student population by relevant stakeholders. One of the milestone achievements was the computerization of all the systems in the institution to improve service delivery. However, little has been achieved as the existing computerized system is less responsive to current objectives and goals of the College(Welsh, Wanberg, Brown, & Simmering, 2003).

The proposed upgrade of the existing IT infrastructure presents growth opportunity as well as wholesome improvement in the level of service delivery. The main benefits that the college will accrue as a result of the new system include; improvement financial management to eliminate cases of erroneous tuition fee estimations. Moreover, it will enable the students to conveniently access and track their academic progress and eliminate the need to physically visit the institution. This can greatly reduce the cost of hiring more staffs to take care of the rising complaints from students. Similarly, the project will improve online registration, especially by the new students. The prospective students will not have to travel far and wide to meet the staffs at the institution in order to register as new students. The system will automatically effect the registration process by the new students thus saving the college thousands of dollars that would be used in hiring additional staffs to handle all manual admission related issues. Therefore, the charter project will enable the college to improve on service delivery with regard to education.

  1. Project Objectives and Expected Benefits

Objective 1 – To investigate the impacts of improving financial transparency

There have been cases of erroneous tuition fee estimation being made by the financial departments at the institution. The need to reduce such incidence has necessitated the upgrade existing computerized system. Therefore, while upgrading the existing computerized system can be perceived as being expensive, it will reduce incidences of financial fraud by the employees of the institution and possibility of students colluding with financial officers at the institution for fraud financial deals (Ozkan & Koseler, 2009).

Objective 2 – To determine effects of improvement in online registration on general enrollment of students.

The proposed upgrade provides a better online platform where the students can initiate registration process depending on the courses they want to pursue at Keller College. The new upgrade eliminates the need for students to physically visit the institution to affect their registration. Similarly, the College will not need to hire more employees for registration of students. The enrolment of students is thus, expected to increase tremendously(Wang & Wang, 2009).

Objective 3 –To determine the effect of the creation of student portal in managing academic records of the students.

 By creating a portal which is automatically generated on successful registration of new students into the college academic program, maintenance of student academic record is made possible. The students are thus able to monitor their academic progress thus promoting transparency in all activities revolving around academics (Wu, Tennyson, & Hsia, 2010).



Measurable Benefits

Metric

Baseline

Target

Expected Improvement

Prospective Students

75,000

90,000

20%

New Students Registration

42,000

55,000

31%

Online Financial Aid Application

33,000

50,000

52%

  1. Project Detail

Problem Description

The Keller College despite having a computerized system, there are still major challenges regarding online registration, the student finance transparency, as well as accessibility of student academic records. Therefore, the institution will need to conduct upgrade to address the challenges above (Shee & Wang, 2008).

Identified Root Causes

The current computerized system is the cause of the existing challenges faced by the institution. It is less responsive to growing demand in both operational and academic needs. It creates unnecessary bottlenecks in operations and academic processes at the institutions(Ozkan & Koseler, 2009).

Proposed Solution

Table 1: impact of the proposed solutions

Current status

Expected improvement

Enrolment of students

70%

150%

Financial transparency

50%

140%

Student academic record storage

40%

140%


Scope Details

In Scope

Out of Scope

Implement both areas of CL: course inventory manager (CIM), catalog manager (CAT).

CIM will be implemented for all careers: UGRD, GRAD

Replacing web sites of academic units or departments.

Automate student registration

Automated updates of individual user’s security in the portal when roles change in

Electronically track student records and courses

Replacing any part or form of advising and degree audit requirement system.

Provide required online course proposal, course change proposal, and course topics forms

Automated updates of degree audit requirement system when catalog updated.

Utilize My.Devry assigned email addresses in the workflow notifications.

Replacing any part of My.Devry, including the schedule of classes and registration.

Project Milestones

Name

Target Date

Comments

Project Kick off

08/20/2017

This will determine the sustainability

M2. Availability of CIM to proposers and approvers for online students’ registration.

12/12/2017

By the student portal should be available

M2. Availability of CAT to proposers and approvers for next generation catalog updates.

02/02/2017

Completion

07/08/2018

This is feasible seen the realization


Team Project Team

Name

Title

Department

Project Role

Lompri Koroma

Project Manager

Academic

Manage

Tianye Lin,

Project Superviser

Academic

Supervise

Maodo Sow

Project Programmer

Acedemc

Implement

Nikhil Vasani

Project Programmer

Academic

Implement

Steering Team

Name

Title

Department

Steering Team Role

Edkins, Ivonna

Project Sponsor

Group President South West Group

Sponsor

May, Vicki

Executive Sponsor

SW Group Director Finance

Executive

Stakeholder Team

Name

Title

Department

Stakeholder Role

Students

Keller’s Students

Academic

Portal Users

Parents, Prospects, High Schools

Outside Users

Prospective Students

Admissions Agents

Admissions

Admission

Catalog user in marketing & recruitment needs

Advisors

Advisors

Registration Dept.

Catalog user in advising

  1. Project Costs & Resource Estimates

Project Costs

Project Expense

Cost Center

Comments

Est. Amount

Advocacy

School Registration

Need advice about the New SIS

$20,000

Planning

School Registration

Make a good planning system

$20,000

Study and Surveys

School Registration

For information gathering

$30,000

Project Support

School Registration

Support for the project process

$60,400

Computing System

Need new computing system

$480,000

$590,000

Total:

Resource Estimation

Role or Name

Department

Est. Hours

Rate

Est. Total

Database Analyst

Registration

450

13.6%

Help Desk Analyst

Registration

300

9.1%

Microcomputer Support

Registration

260

7.9%

Network/Telecomm Support

Registration

500

15.1%

Programmer/Analyst

Registration

420

12.7%

Project Manager

Registration

580

17.5%

Systems Analyst/Programmer

Registration

420

12.7%

Tester/Trainer

Registration

380

11.5%

3,310

Total:

  1. Risks & Communication Plan

Risk Mitigation Plan

Identified Risk

Severity

Probability

Mitigation

Risk 1

High

Low

Mitigation plans

Encounter bugs in online registration

Low

Low

Mitigation Plans

High volume of access

low

low

Mitigation Plans

Communication Plan

Topic

Audience

Frequency/Date

Owner

Kickoff Meetings

School official

08/02/2017

Project Team Meetings

Team

08/12/2017

Technical Design Meetings

Team

08/22/2017

Monthly Project Status Meetings

School official

Every month

  1. Additional Project Details

Reference

Ozkan, S., & Koseler, R. (2009). Multi-dimensional students’ evaluation of e-learning systems in the higher education context: An empirical investigation. Computers & Education, 53(4), 1285-1296.

Shee, Y. D., & Wang, S. Y. (2008). Multi-criteria evaluation of the web-based e-learning system: A methodology based on learner satisfaction and its applications. Computers & Education, 50(3), 894-905.

Wang, T. W., & Wang, C. C. (2009). An empirical study of instructor adoption of web-based learning systems.,. Computers & Learning process, 53(3), 761-774.

Welsh, T. E., Wanberg, R. C., Brown, G. K., & Simmering, J. M. (2003). E‐learning: emerging uses, empirical results and future directions.International Journal of Training and Development, 7(4), 245-258.

Wu, H. J., Tennyson, D. R., & Hsia, L. T. (2010). A study of student satisfaction in a blended e-learning system environment. Computers & Education, 55(1), 155-164.