Project Management Assignment 2

Project Title: Just-In-Time Training Project

Project Start Date: July 1 Projected Finish Date: June 30 (one year later)

Budget Information: The firm has allocated $1,000,000 for this project. Approximately half of these costs will be for internal labor, while the other half will be for outsourced labor and training programs.

Project Manager: Kristin Maur, (610) 752-4896, [email protected]

Project Objectives: Develop a new training program that provides just-in-time training to employees on key topics, including supplier management, negotiating skills, project management, and software applications (spreadsheets and Web development). Develop an approach for measuring productivity improvements from this approach to training on an annual basis.

Success Criteria: This project will be successful if it reduces training costs per employee by 10% or $100/employee/year. It should also be completed in time, be run professionally, and meet all of the requirements. The project sponsor will fill out a customer acceptance/project completion form at the end of the project and give the project at least a 7 out of 10 overall rating.

Approach:

  • Terminate all internal training courses except the Six Sigma training once new courses are developed

  • Communicate to employees the plans to improve internal training and let them know tuition reimbursement will continue as is

  • Work closely with internal manager and employees to determine the best approaches for providing training in supplier management, negotiating skills, project management, and software applications

  • Research existing training and work with outside experts to develop several alternatives for providing each training topic

  • Develop and implement new training

  • Take advantage of new training approaches and technologies and encourage employees to take some training during non-work hours

  • Encourage experts within the company to mentor other workers on current job duties

  • Determine a way to measure the effectiveness of the training and its impact of productivity on an annual basis

Roles and Responsibilities:

Name and Signature

Role

Position

Contact Information

Mike Sundby

Mike Sundby

Project Champion

VP of HR

[email protected]

Lucy Camerena

Lucy Camerena

Project Sponsor

Training Director

[email protected]

Kristen Maur

Kristen Maur

Project Manager

Project Manager

[email protected]

Julia Portman

Julia Portman

Steering Committee Member

VP of IT

[email protected]

Tim Nelson

Tim Nelson

Steering Committee Member

Supplier Management Director

[email protected]

Mohamed Abdul

Mohamed Abdul

Team Member

Senior programmer/analyst

[email protected]

Kim Johnson

Kim Johnson

Team Member

Curriculum designer

[email protected]

Comments: (Handwritten or typed comments from above stakeholders, if applicable)

“I am concerned about people’s reactions to cancelling most internal training and totally changing most training courses. I also hate to terminate some contracts with local training firms we’ve used for several years. We should try to get some of them involved in this project.” Lucy

“I wat to review all of the information related to providing the supplier management training. We need to make something available quickly.” Tim