Project Management – Assignment VI

Assume that planning permission has been obtained and the material has been bought. The remaining activities in a simple project of building a garage are given below. Also the duration in days of each of the activities and the number of people required are shown.


Activity

Description

Immediate preceding activity

Duration (days)

Number of people required

Obtain brick layer

10

Dig the foundation

Lay the base

Build the walls

A and C

Build the roof

Tile the roof

Make window frames

Fit the window frames

D and G

Fit glass to frames

Fit the door

Paint the door and window frames

I and J

Paint the brickwork


(i) a) Using the AOA method draw the network and determine the project duration and the critical path.


b) Draw the network using AON method and find the project duration and the critical path.


c) Develop the tabular analysis and determine the total float, the free float and the independent float for each activity.








(iii) The activities that can be crashed the duration and relevant costs are given in the table below. Assuming that it is worthwhile crashing activities where possible what is the optimum project duration and cost (reduce only one day at a time and use sequenced Gantt charts to justify your selection of activities)?


Activity

Normal duration (days)

Crash duration (days)

Normal cost ($)

Crash cost

($)

100

700

800

1700

500

900

200

400

150

550

30

130

100

200


(iv) Draw the bar chart for the project and show the situation at the end of day 18 when the following activities have been completed.

A, B, and C.


Also activity D has started at the earliest possible time and is 50% complete.


Does the project manager need to take any action? Explain.

(30 marks)

Important Points


Plagiarism and Collusion – Plagiarism involves presenting work, excerpts, ideas, or passages of another author without appropriate referencing and attribution. Collusion occurs when two or more students submit work which is so alike in ideas, content, wording, and/or structure that the similarity goes beyond what might have been mere coincidence. Plagiarism and collusion are very serious offenses and any student found copying another student’s work or quoting work from another source without recognizing and disclosing that source will be penalized.


Please do not cut and paste, do not copy.


Your answers should be submitted on or before 04th June 2017.


Please note that assignments should be submitted on the due date and assignments not submitted on the due date will not be marked. If due to justifiable reasons you are unable to submit the assignment on the due date you must get permission from the Institute giving a specific date (which should be reasonable under the circumstances) that you will submit the assignment.



3