Hello Class and Prof. The time estimates are in hrs. Complete final inspections A-complete elevator inspection and certification B-Perform architects...
Hello Class and Prof.
The time estimates are in hrs.
Complete final inspections | Predecessor | |||
A-complete elevator inspection and certification | 10 | 12 | 14 | |
B-Perform architects inspection | 12 | 14 | 15 | |
C-Perform Fire Marshall's inspection | 12 | 13 | ||
D-Perform demonstration of elevator | ||||
E- Issue final completion documents | D,E |
Critical Path, Slack Time:
Results | |||||
Activity | Early Start | Early Finish | Late Start | Late Finish | Slack |
12 | 12 | 0 | |||
12 | 25.8333 | 12 | 25.8333 | 0 | |
25.8333 | 37.3333 | 25.8333 | 37.3333 | 0 | |
37.3333 | 43.3333 | 37.3333 | 43.3333 | 0 | |
43.3333 | 44.3333 | 43.3333 | 44.3333 | 0 | |
| Project | 44.3333 |
|
|
|
Date: April 28, 2017
To: Jay Pender
From: Dameon Dunkley
Re: Building 4, Unit 10. Elevator completion
We are two days away from completing this site application. All dates are set and waits, the reminding task listed is graph in processor is accurate that is 44.33 hours left. As shown above it would take less that two days of work to complete this application. We are on schedule. Thank you.
Dameon Dunkley.