Hello Class and Prof. The time estimates are in hrs. Complete final inspections A-complete elevator inspection and certification B-Perform architects...

Hello Class and Prof.

The time estimates are in hrs.

Complete final inspections

Predecessor

A-complete elevator inspection and certification

10

12

14

B-Perform architects inspection

12

14

15

C-Perform Fire Marshall's inspection

12

13

D-Perform demonstration of elevator

E- Issue final completion documents

D,E

Critical Path, Slack Time:

Results

Activity

Early Start

Early Finish

Late Start

Late Finish

Slack

12

12

0

12

25.8333

12

25.8333

0

25.8333

37.3333

25.8333

37.3333

0

37.3333

43.3333

37.3333

43.3333

0

43.3333

44.3333

43.3333

44.3333

0

 

Project

44.3333

 

 

 

Date: April 28, 2017

To: Jay Pender

From: Dameon Dunkley

Re: Building 4, Unit 10. Elevator completion

We are two days away from completing this site application. All dates are set and waits, the reminding task listed is graph in processor is accurate that is 44.33 hours left. As shown above it would take less that two days of work to complete this application. We are on schedule. Thank you.

Dameon Dunkley.