PLEASE DRAW THE NETWORK DIAGRAM AND FILL THE TABLE WITH GIVEN INFORMATION

CVE 470 FINAL PROJECT


QUESTION 1.


PLEASE DRAW THE NETWORK DIAGRAM AND FILL THE TABLE WITH GIVEN INFORMATION


Important Dates/Datelines for Project Schedule Revisions:

2-8 activity revised start date T1*= 30 (in other words this activity MUST be start at 30th day!)

10-14 activity revised start date T2*= 55

10-18 activity revised start date T3*= 35

14-22 activity revised start date T4*= 60

X IS THE LAST NUMBER OF YOUR UNIVERSITY ID

Critical Path

activity

i-j

Duration

tij

i Node

TEi TGi

j Node

TEj TGj

i-j Activity

tEBij tESij tGBij tGSij

Floats

TBij SBij

0 – 2

X

0

20

20

30

0

10

20

30

20

10

0 – 4

12

0

20

12

37

0

12

25

37

25

0

0 – 6

9

0

20

9

54

0

9

45

54

45

0

2 – 8

15

20

30

35

45

20

35

30

45

10

0

4 – 8

6

12

37

35

45

12

18

39

45

27

17

4 – 10

X

12

37

35

45

12

20

37

45

25

15

4 – 12

-

12

37

16

61

12

12

61

61

49

4

6 – 12

7

9

54

16

61

9

16

54

61

45

0

8 – 10

-

35

45

35

45

35

35

45

45

10

0

8 – 14

11

35

45

60

60

35

46

49

60

14

14

10 – 14

5

55

55

60

60

55

60

55

60

0

0

10 – 16

9

35

45

44

54

35

44

45

54

10

0

10 – 18

6

35

45

41

58

35

41

52

58

17

0

12 – 20

13

16

61

48

74

16

29

61

74

45

19

18 - 20

7

41

58

48

74

41

48

67

74

26

0

18 – 22

12

41

58

70

70

41

53

58

70

17

17

14 – 22

10

60

60

70

70

60

70

60

70

0

0

16 – 22

16

44

54

70

70

44

60

54

70

10

10

18 – 24

14

41

58

85

85

41

55

71

85

30

30

20 – 24

11

48

74

85

85

48

59

74

85

26

26

22 - 24

15

70

70

85

85

70

85

70

85

0

0

QUESTION 2.

Find a site plan (mobilization plan) of a real project that shows site units (workshops, technical office, stores, dormitories, tower cranes and the construction area itself …), service roads (haul roads), walkways.. i.e transportation plan, utilities (water, drainage, electricity …), prevailing wind, nearby structures etc. (Just copy and paste)

Please give your critics according to the information given in our course.

NOTE: You can find it from real projects from your jobsite or from your friends, networks or internet, books or any other sources…