I need a simulation run using crystal ball application. The excel and instructions are included.
Run Simulation to show your 90% confidence for Total contingency duration and Total contingency cost estimation.
2.1 First, you will run simulation for 90% confidence of your contingency duration
2.1.1 You can use BetaPert distribution for your input assumptions.
2.1.2.Define your individual risk durations as assumptions
2.1.3 Define total contingency duration as Forecast
2.1.4 Run simulation and show 90% confidence
2.2 Repeat step #2.1 for contingency cost and show 90% confidence
Submit Excel with simulation data and charts for step #2.1 and #2.2.