(1) Given the following on 5 independent projects: Project IRR Beta RADR Accept/ Reject A 7.01% 0.2 B 11.90% 1 C 14.50% 1.2 D 11.00% 0.8 E 18.
2
Calculate the risk adjusted discount rate for each project and determine whether each project should be accepted or rejected. Rm = 12% and Rf = 5%
Enter your answers for RADR as a percentage accurate to one decimal place and enter the % sign as well. eg 10.1 should be entered as 10.1%
For the accept/ reject decision enter the word accept or reject in lowercase.
Do not use commas.
Do not use leading zeros.