(TCO C) A project to remodel a bathroom has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and...
4. (TCO C) A project to remodel a bathroom has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and perform a backward pass to answer this question.)
ActivityDurationPredecessors
A2 months---
B4 months---
C4 months---
D1 monthA
E5 monthsB
F2 monthsB, C
G1 monthC
H3 monthsE, F, G
I2 monthsD, E
J2 monthsG, H
- What are the critical path activities? (5 points)
- What is the project's scheduled completion time? (5 points)
- What is the slack or float for Activity A? Show your calculations. (5 points)
- What is the slack or float for Activity E? Show your calculations. (5 points)
- What is the slack or float for Activity F? Show your calculations. (5 points)
- What is the slack or float for Activity G? Show your calculations. (5 points)
(Points : 40)