(TCOs A and B) A Monte Carlo analysis does all of the following, except A. provide the probability of competing the project on a given day. determine...

(TCOs A and B) A Monte Carlo analysis does all of the following, except

A. provide the probability of competing the project on a given day.

B. determine what methodology to employ in risk management.

C. maintain the risk register.

D. evaluate the effectiveness of risk responses.