Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.
1) What is the expected time for activity c? A. 5.167 B. 3 C. 4.28 D. 6 2) What is the variance for activity A?
1) What is the expected time for activity c?
A. 5.167
B. 3
C. 4.28
D. 6
2) What is the variance for activity A?
A. 3.33
B. 2.77
C. 5.31
D. .674
3) Assume there is one critical path of (A, B, C, E) what is the project variance?
A. 5.583
B. 6.313
C. 7.421
D. 8.667