Answered You can hire a professional tutor to get the answer.
1) You have the following results for a given period: Expected completion time of the given project = 48 Variance of project completion time = 6.
1) You have the following results for a given period:
Expected completion time of the given project = 48
Variance of project completion time = 6.25
What is the probability of completing the project over 46 days?
Can you tell me how to figure this and what the answer is?