4. From the EOQ, Q is 100, and annual demand is 500. What is the length of the order cycle?
· 4. From the EOQ, Q is 100, and annual demand is 500. What is the length of the order cycle?
· select
· 47 days
· 365 days
· 100 days
· 121 days
· 73 days
· 5. Daily usage is 5, and lead time to replenish is 12 days. What is the ROP?
· select
· 0
· 5
· 60
· 12
· 2
· 6. A manager wants no more than 5% risk of stockout. What value of z is appropriate?
· .92
· -1.68
· 1.65
· 1.88
· 2.28