A company manufactures a product which requires four hours per unit of machine time. Machine time is a bottleneck
A company manufactures a product which requires four hours per unit of machine time. Machine time is a bottleneck
resource as there are only ten machines which are available for 12 hours per day, five days per week. The product has selling price of $ 130 per unit, direct materials costs of $50 per unit, labour costs of $40 per unit and factory overhead costs of $20 per unit. These costs are based on weekly production and sales of 150 units.
What is the throughput accounting ratio?
A) 1.33
B) 2.00
C) 0.75
D) 0.31