Answered You can hire a professional tutor to get the answer.
A firm has 200 units of a production in inventory. The forecasts are 40 units for week . An MPS quantity of 50 units is planned to arrived on period...
A firm has 200 units of a production in inventory. The forecasts are 40 units for week . An MPS quantity of 50 units is planned to arrived on period 2. Customers orders are 40 for period 1, 10 for period 2 and 50 for period 3. Present computation to estimated on hand inventory at the end of period 3, and the result.