A network consists of the following list. Times are given in weeks. Activity Preceding Duration A -- 9 B A 2 C A 12 D A 5 E B 6 F B 8 G C, F 3 H D 2...

a.             Draw the network diagram.

b.            Which activities form the critical path?

c.             How much slack exists at activities A and F?

d.            What is the duration of the critical path?