A production process at Kenneth Day Manufacturing is shown in Figure S7.
A production process at Kenneth Day Manufacturing isshown in Figure S7.9. The drilling operation occurs separatelyfrom, and simultaneously with, the sawing and sanding operationsDrilling6 units/hrSawing0.7 units/hrAssembly0.7 units/hrAssembly0.7 units/hrAssembly2 units/hrWeldingsanding6 unit /hrA product needs to go through only one of the three assembly operations(the operations are in parallel).a) Which operation is the bottleneck?