A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before day...
A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before day ________ (rounded to nearest day)._631_689_807_833_1009