 A small project has 7 activities and the time in days for each activity is given below:

a. Draw the network diagram.

b. Compute early start, late start times.

c. Calculate total float for each activities.

d. Determine critical activities and critical path.

e. Find the project duration

4. A small project has 7 activities and the time in days for each activity is given below: a. Draw the network diagram b. Compute early start, late start times. c. Calculate total float for each activities. (1. Determine critical activities and critical path.e. Find the project duration. mA — 6B — 8C A 3D A 4E B,D 6F B, C MD 10G E 3