a time study has determined that the standard time for a job is 5.0 minutes per unit produced.
a time study has determined that the standard time for a job is 5.0 minutes per unit produced. If a worker produced 120 units in an eight-hour day, what would their days' [ay be of the basis rate was $7 per hour and the premium payment system paid on a 100% basis?
a. greater than $100
b. between $75 and $99.99
c. between $65 and $74.99
d. between $55 and $64.99
e. less than $55