Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.

QUESTION

ABC Construction has developed the following set of activities for its budgeting process.

a) Using the Normal Times, what is the critical path and project completion time for the budgeting process?  Also, what is the cost to complete the project based on the Normal Times?

b) If we want to reduce the project completion time to the minimum possible time by crashing activities, what is the new project completion time and what is the new total project cost?

c) Modify the problem as follows.  There is now an indirect cost of $75 per day, which is in addition to the cost identified above.  There is also a penalty cost of $200 per day for any project completion time over 11 days.  What is the minimum cost schedule for the project and what is the total cost for this schedule?  Identify what are the time and the path of this minimum cost schedule.

d)  Suppose that the company wants to crash the project 4 days.  Based on the information provided in the table and in part c) and the results from part c), what would the minimum penalty cost have to be for this to be supported by the economics in the problem?  Assume that the indirect cost remains at $75 per day.  

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question