Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.
Activity Predecessor Normal time (days) Crash time (days) Normal cost Rs Crash cost Rs A - 3 2 8000 14000 B - 2 1 12000 19000 C A 5 3 20000 28000 D B...
Activity
Predecessor
Normal time (days)
Crash time (days)
Normal cost
Rs
Crash cost
Rs
A
-
3
2
8000
14000
B
-
2
1
12000
19000
C
A
5
3
20000
28000
D
B
5
3
15000
23000
E
C,D
6
4
18000
28000
F
C,D
2
1
6000
10000
G
F
2
1
5000
10000
i) Draw the network diagram
ii) Find the paths and identify the critical path
iii) Find the duration of the project
iv) Calculate the cost slope for each of the activities
v) What is the total project cost using the normal times?
vi) If the duration of the project is to be reduced to 12 days what will be the project cost?