QUESTION

Along the critical path? Immed. Predec. A) What action would you take to reduce the critical path by one day?

Along the critical path? Immed. Predec. A) What action would you take to reduce the critical path by one day? Crash Cost per day $ 600 $ 900 $ 1,000 Max. Since A is the critical activity with the lowest crash cost per day, crash A first. B) To crash the critical path a second day, crash B since it has the second lowest cost. C) What is the total cost of the 2-day reduction?

Show more