An ABC manufacturing company produce 1000 units of ceiling fans daily and they are using batch production, Cycle time is 8 hours, setup time is 4...
An ABC manufacturing company produce 1000 units of ceiling fans daily and they are using batch production, Cycle time is 8 hours, setup time is 4 hours and non-operation time= 1 hours. company is using a facility in which parts are made in one operation (n = 1). Shift per week = 6 hours per shift = 8. MTBF = 8 hours, MTTR = 2 hours.
Calculate in following
production rate Rp (units/hours)
production capacity PCw (units/week)
Utilization U
Availability A
Manufacturing lead time MLT (hours)
Work in progress WIP