Answered You can hire a professional tutor to get the answer.
An assembly line is to operate eight hours per day with a desired output of 240 units per day. The following table contains information on this...
An assembly line is to operate eight hours per day with a desired output of 240 units perday. The following table contains information on this product’s task times and precedencerelationships:TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR—AAAB, CC, DE, FGa. Draw the precedence diagram.b. What is the workstation cycle time?c. Balance this line using the longest task time.d. What is the efficiency of your line balance?
PRECEDENCE DIAGRAM B A A C E D TASKABCDEFGH TIME START TIMEFINISH TIMEFLOATPREDECESSORARLIEST LATEST EARLIEST LATESTE60006060080A6060140140020A60120801406050A60...