Waiting for answer This question has not been answered yet. You can hire a professional tutor to get the answer.

QUESTION

An auditor is currently carrying out a post-completion audit of a project originally estimated to be worth $100,000.

An auditor is currently carrying out a post-completion audit of a project originally estimated to be worth $100,000. From the post-completion audit, the findings are that results from the 3rd year will be $90,000, while that of the 4th and 5th years will be $60,000 and $40,000 respectively.

There's a growing concern that the projected cash flows might not be feasible, even when they were originally outlined as follows:

1st year = $60,000

2nd year = $80,000

3rd year = $70,000

4th year = $80,000

5th year = $60,000

Assuming that all cash flows increase and the cost of capital for this company will be 12% p.a. can determine whether the investment should continue or not?

Show more
LEARN MORE EFFECTIVELY AND GET BETTER GRADES!
Ask a Question