an automobile detail shop has the following jobs waiting to be processed. all jobs (cars requiring detailing) must first be cleaned, then waxed.
an automobile detail shop has the following jobs waiting to be processed. all jobs (cars requiring detailing) must first be cleaned, then waxed.
Job C1 C2 C3 C4 C5
Cleaning Time 2 9 5 6 8
Waxing Time 3 3 7 11 5
A. What processing sequence will minimize the makespan for these jobs?
B. What is the minimums makespan for this set of five jobs