Answered You can buy a ready-made answer or pick a professional tutor to order an original one.
analyze the case study “Ariba Implementation at Med-X: Managing Earned Value” and apply earned value metrics to make decisions about the project in a short paper
Many project managers employ an earned value system to monitor their projects. In Project Management: The Managerial Process, Larson and Gray (2014) define the earned value of a project as “the percent complete times its original budget. Stated differently, EV [earned value] is the percent of the original budget that has been earned by actual work completed.”In this assignment, you will analyze the case study “Ariba Implementation at Med-X: Managing Earned Value” and apply earned value metrics to make decisions about the project in a short paper.
Overview: Many project managers employ an earned value system to monitor their projects. In Project Management: The Managerial Process, Larson and Gray
(2014) define the earned value of a project as “the percent complete times its original budget. Stated differently, EV is the percent of the original budget that has
been earned by actual work completed” Earned value analysis determines if you are getting value for the work completed and the money spent during a specific
time frame.
Prompt: Analyze the case study Ariba Implementation at Med-X: Managing Earned Value (this case study can be located in your custom Textbook/Case Study
bundle). Using earned value analysis, you will determine why the company’s e-procurement implementation project is not going according to plan. Once a cause
has been discovered, you will make a recommendation to fix the problem.
Specifically, the following critical elements must be addressed:
Cost: Give an estimate of the cost of the project.
Time: Give an estimate regarding how long the project will take.
Cause: Based on your analysis, give an explanation as to why the company’s project is not going according to plan. What is wrong with the project?
Support your explanation with evidence from your analysis.
Recommendations: What action(s) do you recommend to address the cause of the problem? Support your recommendations with evidence from your
analysis.
Application: How do you foresee using earned value metrics on your own projects currently or in the future?
Guidelines for Submission: Your case study analysis must be submitted as a 1- to 2-page Microsoft Word document with double-spacing, 12-point Times New
Roman font, one-inch margins, and sources cited in APA format.
Please refer tot eh QSO 680 rubic for complete instructiions.
- @
- 2015 orders completed
- ANSWER
-
Tutor has posted answer for $50.00. See answer's preview
***** Implementation ** ***** ******** Earned ************ **** ******** **** *** technical infrastructure *** the ******** ************* *** ***** *** ******* *** *** *** software ************* ** 118 ***** that for *** ********* infrastructure ** *** ******* the ******** customization is greatly within *** ****** *** *********** ** *** *** ** ****** *** budget *** ***** **** can ** ******** ** **** this *** ***** **** *** *** project ** ***** to ** $183122995 implying **** ** is within the ****** ** ********