Assignment Purpose:To apply project management techniquesAssignment DescriptionThe factors for planning a successful EHR implementation are below including each activity's duration and predecessor(s):
Assignment Purpose:
To apply project management techniques
Assignment Description
The factors for planning a successful EHR implementation are below including each activity's duration and predecessor(s):
1. Create the PERT chart for this implementation
2. Indicate the critical path on the PERT chart
3. Design the GANTT chart for this implementation
Activity Duration (days) Predecessor
A Create the EHR vision 5 -
B Identify the planning horizon 10 A
C Obtain buy-in from affected parties 30 B
D Develop a financing and acquisition strategy 10 C
E Develop functional, data, and technical strategies 45 C
F Conduct vendor selection 45 D, E
G Plan the EHR implementation 15 C, E, F
H Conduct benefits realization study 10 A-G